Sarawak Energy Strengthens Electricity Supply in Northern Region Through Sarawak Grid Interconnection
LAWAS
18 NOVEMBER 2026
Sarawak Energy remains committed to strengthening the reliability of electricity supply across Sarawak, including the Northern Region, through continuous efforts to enhance the state's electricity infrastructure.
The connection of Limbang and Lawas to the Sarawak electricity grid was completed in July this year, reducing reliance on diesel-based power generation. Both districts now benefit from an electricity supply system predominantly powered by hydropower, Sarawak's primary source of renewable energy.
The symbolic launch of the 275kV grid connection to Lawas and Limbang was officiated by the Right Honourable Datuk Patinggi Tan Sri (Dr) Abang Haji Abdul Rahman Zohari Bin Tun Datuk Abang Haji Openg, Premier of Sarawak, in Trusan, Lawas on 18 November in conjunction with the Groundbreaking Ceremony for the New Trusan Water Treatment Plant Project.
Sarawak Energy Group Chief Executive Officer, Dato Ruslan Abdul Ghani said the successful integration of both districts into the Sarawak electricity grid marked a significant milestone in enhancing the reliability of electricity supply in the Northern Region.
“With Lawas and Limbang now connected to the Sarawak electricity grid, the resilience of the electricity supply system has been strengthened, ensuring a more stable and reliable supply for consumers.
“At the same time, this infrastructure provides a stronger foundation to meet growing energy demand and support local economic development. It also paves the way to extend electricity supply to rural areas such as Batu Danau and Ulu Medamit in the future.”
“This is in line with Sarawak Energy’s commitment to providing reliable, sustainable and affordable electricity to support Sarawak’s economic development and the well-being of its communities,” he explained.
The Lawas 275kV Substation was commissioned on 21 November 2025, enabling Lawas to be connected to the Sarawak grid. Electricity supply from the grid to the Lawas distribution network commenced on 4 December 2025.
This was followed by Limbang on 31 July 2026, with the commissioning of the 275kV Limbang Town Substation and the energisation of the 275kV Bunut-Medamit-Limbang transmission line.
The grid connection project to Limbang involved approximately 228 kilometres of 275kV transmission lines, supported by transmission towers and monopoles, extending from Bunut through Medamit to the Limbang Town Substation.
Sarawak Energy Group Chief Executive Officer Dato Ruslan Abdul Ghani (second left) poses for a group photo with the Premier of Sarawak and other dignitaries at the launch event.
Dato Ruslan (fourth left) joins the Premier of Sarawak and other dignitaries on stage for the symbolic launch of the 275kV grid connection to Lawas and Limbang.